Project Portfolio
Project and portfolio management from opportunity to close — plan and critical path, cost estimates and budgets, earned value, margin-safe pricing and customer quotations, contracts, milestone and progress billing, revenue recognition, timesheets, resources and governance.
Project Portfolio
Project Portfolio (PPM) runs a project from the first opportunity to the final close in one workspace: plan the work, estimate and approve its cost, price it, quote the customer, sign the contract, deliver, bill, recognize revenue and close. Portfolio leaders see the health, cost and schedule performance of every project they may view on one command center.
Download the complete guide as PDF in English and Arabic from Project Portfolio Guide. Status flows for every record are on Project Portfolio Workflows.
#Why finance can trust it
| Principle | What it means |
|---|---|
| Cost, price and profit stay apart | Project cost (estimates and budgets), commercial price (pricing scenarios and quotations) and profitability each have their own permissions and records. Pricing never changes cost. |
| One source of actual amounts | Actual cost and recognized revenue come from posted General Ledger lines tagged with the project. Each ledger line is counted once. |
| No duplicate billing | Project invoices are raised from the project's Contract & billing tab through Accounts Receivable, never from the sales order, so the customer is billed once. |
| Postings are idempotent | Labour cost, billing and revenue journals carry a unique key per timesheet, billing event and period, so a retry never posts twice. |
| People decide | Estimates, budgets, change requests, timesheets, revenue true-ups and AI drafts wait for a person who holds the approval permission. AI never prices, posts or issues a quotation. |
#Core concepts
| Concept | What it is |
|---|---|
| Portfolio and program | A portfolio groups projects by strategy or business unit. A program groups related projects inside a portfolio. |
| Project | The unit of delivery: customer, contract type, project type, dates, priority, currency, team and lifecycle stage. |
| Lifecycle stage | Opportunity, Feasibility, Planning, Costing, Commercial, Contracted, Execution, Closing, Closed or Cancelled. |
| Work breakdown | Phases, sub-phases, work packages, activities, tasks and subtasks with durations, effort and percent complete. |
| Dependency | Finish-to-start, start-to-start, finish-to-finish or start-to-finish link with lag or lead days. |
| Baseline | A frozen copy of the plan's dates and costs used to measure variance. |
| Cost estimate revision | Versioned estimate lines per task and cost category, submitted and approved. One revision is open at a time. |
| Costing snapshot | The frozen, approved cost basis that pricing and quotations use. Employee rates are not exposed. |
| Pricing scenario | A price built from the cost basis by margin or markup, checked against the margin floor. |
| Budget | Original, approved and revised versions. The approved budget is the earned value baseline. |
| Earned value | PV, EV, AC, BAC, EAC, ETC, VAC, CPI and SPI, measured once a day per project. |
| Contract | Billing basis, value and retention, created when the quotation becomes a sales order or recorded by hand. |
| Revenue true-up | The difference between revenue earned under the policy and revenue already invoiced, posted after approval. |
#Getting started
- Platform: enable the
ppmapp in the tenant's subscription. The menu then shows Project Portfolio, which opens the dashboard at/ppm. - Tenant administrator: assign the PPM permissions to the right roles. View and Search on most areas are basic permissions; costing, budgets, commercial, contracts and billing are not.
- Open Settings: set the project code prefix, time zone, base currency, decimal places, minimum margin, maximum discount, default revenue policy and whether approved labour cost posts to the General Ledger.
- Open Resources and add people, teams, contractors and equipment with their hourly cost.
- Open Portfolios & programs and create the strategic groups you report on.
- Create the first project on Projects and follow the Next best step card in its workspace.
#Permissions
| Permission resource | Protects |
|---|---|
PpmDashboard |
The portfolio command center and role views |
PpmPortfolios / PpmPrograms |
Portfolios and programs |
PpmProjects |
Projects, the workspace, team and stage changes. Manage sees every project — others see the projects they own, manage or belong to — and edits Settings |
PpmSchedule |
Plan, Gantt, Kanban, calendar and milestones |
PpmCosting |
Cost estimates. Approve approves estimate revisions |
PpmBudgets |
Budget versions and the earned value baseline |
PpmCostConfidential |
Confidential, salary-based rates on estimate lines |
PpmCommercial |
Costing snapshot, pricing scenarios and the Project Quote Studio |
PpmContracts |
Contracts and change orders |
PpmBilling |
Billing, revenue true-ups and profitability |
PpmResources |
The resource catalog, allocations and load |
PpmTimesheets |
Logging time. Approve approves the team's timesheets |
PpmRisks / PpmIssues / PpmChanges |
Risks, issues and change requests |
PpmAi |
Project intake drafts. Approve applies a draft |
Each workspace tab appears only when the role can view its area, so a sales user can price and quote without seeing confidential cost rates.
#The project lifecycle
The lifecycle stepper at the top of the workspace shows the stage and the next best step, with a button that opens the right tab.
| Stage | How the project gets there | Typical work |
|---|---|---|
| Planning | Creating the project, or applying an AI intake draft (status Draft) | Scope, work breakdown, dependencies, milestones |
| Costing | Adding the first estimate revision | Estimate lines, submission |
| Commercial | Approving the estimate, or quoting the customer | Pricing scenarios, Project Quote Studio |
| Contracted | Recording a contract | Billing basis, value, retention |
| Execution | Start execution, or converting the project's quotation to a sales order | Progress, time logging, billing |
| Closing | Begin closing | Settle open items, lessons learned |
| Closed / Cancelled | Close project / Cancel project | Read-only; Reopen project continues |
The stepper also shows Opportunity and Feasibility, the pipeline stages before planning. Stages only move forward on their own, and the first move also turns a Draft project Active. Put on hold pauses delivery and Resume continues it. Close project is blocked while change requests, submitted timesheets or revenue proposals are still open.
#Planning and scheduling
- Plan tab: phases and tasks with durations, planned effort and percent complete. Summary items roll up dates and progress from their children.
- Dependencies: finish-to-start is the usual link; lag delays the successor and a negative value overlaps the tasks. A task cannot depend on itself, and a loop is reported.
- Critical path: Recalculate runs forward and backward passes over the working calendar, sets total and free float and flags critical tasks. The Gantt and the predicted finish use the result.
- Baselines: capture a baseline when the plan is agreed. Variance compares the working plan with it; baselines are never overwritten.
- Milestones and deliverables: a contractual milestone with a billing amount becomes billable once completed. Deliverables carry acceptance criteria.
- Boards: Kanban moves tasks between Not started, In progress and Done; Calendar shows task finishes and milestones by month; Milestones shows each milestone's due date and whether it is planned, overdue or done.
#Cost, budgets and earned value
- New estimate revision on the Cost tab. Add lines per task and cost category: quantity × unit cost, hours × rate, plus a contingency amount. Assumptions and exclusions travel into pricing and the quotation.
- Submit and Approve the revision. Approving freezes the costing snapshot, supersedes earlier revisions, moves the project to Commercial and prepares a standard-margin pricing scenario.
- Create the budget from the approved estimate and approve it. The approved budget is the earned value baseline.
- Earned value is measured once a day (UTC date) for every active project: planned value moves with the calendar even when nothing was booked.
| Measure | Meaning |
|---|---|
| CPI | Earned value ÷ actual cost. Above 1 means the work done cost less than planned. |
| SPI | Earned value ÷ planned value. Above 1 means more work was done than planned by today. |
| EAC / ETC / VAC | Forecast total cost, cost still to come, and the variance against the budget at completion. |
Fifteen cost categories are provided: labour, overtime, consultants, subcontractors, materials, procurement, equipment, rental and depreciation, logistics, travel, software, infrastructure, overhead, contingency and other.
#Pricing and quoting
- Commercial tab: the frozen cost basis, pricing scenarios and the project's quotations. A scenario uses Margin (profit ÷ price) or Markup (profit ÷ cost); a 25% markup is only a 20% margin.
- Margin floor: the minimum margin from Settings. A scenario below it is flagged.
- Standard scenario: approving an estimate prepares a scenario at the minimum margin plus 10 points, never below 20%, so the project can be quoted at once.
- Project Quote Studio (
/sales/project-quotesin Sales): five steps — Customer, Project, Pricing, Terms and Review. The price ladder shows cost, floor and list price; the discount control shows the live margin; taxes are calculated after discount; the payment plan comes from contractual milestones. - Guardrails: a discount above the maximum discount, or a price below the margin floor, sends the quotation for approval before it can be issued to the customer.
- Getting ready to quote: projects that are not yet quotable show a track of Estimate cost, Submit, Approve and Price, with buttons to take the next step when you hold the permission.
#Contracts, billing and revenue
| Area | How it works |
|---|---|
| Contract from the quotation | When the project's quotation is converted to a sales order, a milestone-billed contract is created at the quotation's value net of discounts and before tax, an execution baseline of the plan is captured and the project moves to Execution. |
| Recorded contract | Record contract on Contract & billing sets the billing basis (fixed price, milestone, progress, time and materials or cost plus), value and retention. |
| Change orders | An approved change request with a price impact adds a change order and raises the contract value. |
| Billing | Bill completed contractual milestones or progress. Each bill raises one Accounts Receivable invoice and withholds retention automatically. A bill cannot exceed what is left on the contract. |
| Revenue recognition | Every contracted project keeps one open true-up proposal in step with earned revenue. After approval, only the difference between earned and invoiced revenue posts, to unbilled receivable or deferred revenue. |
| Profitability | Estimated cost, contract value, actual cost, invoiced amount and expected, actual and forecast profit — without employee-level detail. |
Revenue policies: Cost to cost (share of budget spent), Output (measured progress), Milestone (milestones completed), Time and materials (as billed) and Straight line (spread over the planned dates). A contract's billing basis can imply its own policy.
#Posting roles
| Role | Default account | Used for |
|---|---|---|
PPM.Wip |
1400 | Debit for approved labour cost |
PPM.LaborAbsorption |
5100 | Credit for approved labour cost |
PPM.RevenueRecognized |
4000 | Revenue true-ups |
PPM.UnbilledReceivable |
1300 | Earned revenue not yet invoiced |
PPM.DeferredRevenue |
2400 | Invoiced revenue not yet earned |
PPM.RetentionReceivable |
1310 | Retention withheld on project invoices |
The posting rules are seeded per company when the accounts exist, and can be changed in General Ledger posting rules.
#Time and resources
- Resources: people, teams, contractors, consultants, equipment, machinery and vehicles with skills and an hourly cost. Inactive resources cannot be allocated or log time.
- Load: a heatmap of booked hours against each resource's working calendar — Light (below 60%), Healthy (60–90%), Full (90–100%) and Over-booked (above 100%) — over 2, 4 or 8 weeks.
- Timesheets: log the week against project tasks, mark billable and overtime hours and submit. A submitted week is locked until it is approved or rejected with a reason.
- Labour cost: approved hours add to task actuals. Overtime is costed at 1.5× the rate. When labour posting is on, approval posts project WIP against labour absorption, one journal per company.
#Governance
- Risks: probability and impact from 1 to 5 place each risk on the matrix; the response is mitigate, avoid, transfer or accept.
- Issues: low, medium, high or critical. Overdue high and critical issues are escalated by the nightly job and their owner is notified.
- Change requests: schedule, cost and price impact. Approving adjusts the forecast and budget and adds the price impact to the contract.
- Decision log and lessons learned: what was decided, by whom and when, and what the team learned, survive handovers.
- Approvals: one queue of estimates, budgets, change requests, timesheets and AI drafts, oldest first. Approval rules in Settings decide who approves by subject and amount range; with no rule, one approval is enough — from Finance for estimates, budgets and billing, from a Manager for everything else.
#Dashboards and AI
- Command center: Executive, Project Manager, Finance, Sales and Operations views of the same data — portfolio health, cost vs schedule (CPI against SPI), budget burn, the watchlist and smart insights.
- Health score: blends cost efficiency, schedule efficiency, finish-date slippage, overdue milestones, open issues, open risks and progress into On track, At risk or Critical.
- Project intake: describe new demand on Portfolios & programs; an AI draft with phases is proposed. Nothing is created until a person chooses Create project.
- AI tools:
Ppm.GetDashboardandPpm.SearchProjectsare read-only;Ppm.ProposeProjectDraftonly stores a proposal. Each needs the matching PPM permission.
#Background jobs
| Job | Schedule | What it does |
|---|---|---|
ppm:rollup |
Every 15 minutes | Rolls up cost per task and project, measures earned value and captures profitability for changed projects |
ppm:sweep |
Daily at 02:00 | Logs overdue milestones, escalates overdue high and critical issues, queues the daily earned value point for active projects and keeps revenue true-up proposals current |
Both run per tenant; the queue and the time zone of the schedule come from the PpmJobs configuration section.
#Page reference
| Page | Address | Permission |
|---|---|---|
| Command center | /ppm, /ppm/dashboard/{role} |
PpmDashboard |
| Projects | /ppm/projects |
PpmProjects |
| Project workspace | /ppm/projects/{id} |
PpmProjects, plus each tab's area |
| Kanban | /ppm/projects/{id}/kanban |
PpmSchedule |
| Calendar | /ppm/projects/{id}/calendar |
PpmSchedule |
| Milestones | /ppm/projects/{id}/milestones |
PpmSchedule |
| Portfolios & programs | /ppm/portfolios |
PpmPortfolios, PpmPrograms, PpmAi |
| Resources | /ppm/resources |
PpmResources |
| Timesheets | /ppm/timesheets |
PpmTimesheets |
| Approvals | /ppm/approvals |
The approval permission of each subject |
| Settings | /ppm/settings |
PpmProjects (Manage to change) |
| Project Quote Studio | /sales/project-quotes |
SalesOpportunities and PpmCommercial |
Every page has in-app help (F1) in English and Arabic that explains each dialog field and shows the page's step in the project workflow.
#Troubleshooting
| Symptom | What to do |
|---|---|
| A workspace tab is missing | The role cannot view that area, for example Cost or Contract & billing. |
| New estimate revision is disabled | Another revision is still open. Submit, approve or reject it first. |
| A project is not offered in the Project Quote Studio | Approve its estimate; the standard scenario is created on approval. Use Getting ready to quote to take the next step. |
| The quotation waits for approval | The discount is above the maximum discount or the price is below the margin floor. |
| Bill is not offered for a milestone | Complete the milestone in the plan and give it a billing amount. |
| No point on the cost vs schedule chart | The project has no estimate or budget, or no measured progress yet, or today's measurement has not run. |
| Close project is blocked | Decide open change requests, submitted timesheets and revenue proposals first. |
| Labour cost does not reach the ledger | Turn on labour cost posting in Settings; it applies to timesheets approved from then on. |